Question: Should a GC issue a purchase order or a subcontract agreement for each of the following different concrete scopes: a Form purchase. b Form rental.
Should a GC issue a purchase order or a subcontract agreement for each of the following different concrete scopes:
a Form purchase.
b Form rental.
c Rebar supply.
d Rebar installation.
e Concrete pump.
f Concrete purchase.
g Slab finishing h Tilt-up crane.
Step by Step Solution
3.39 Rating (158 Votes )
There are 3 Steps involved in it
A General Contractor GC typically utilizes different contractual instruments depending on the nature and scope of the work being performed For the var... View full answer