In a company weekly minimum and maximum consumption of material A are 25 and 75 units respectively.

Question:

In a company weekly minimum and maximum consumption of material A are 25 and 75 units respectively. The reorder quantity as fixed by the company is 300 units. The material is received within 4 to 6 weeks from issues of supply order. Calculate minimum level and maximum level of material A.