Question: An engineer prepares a report to evaluate a project using PW and IRR. Just before submitting the report, he spills coffee on it, making the

An engineer prepares a report to evaluate a project using PW and IRR. Just before submitting the report, he spills coffee on it, making the first digit of the 2-digit IRR unreadable. The second digit is a 2. The PW is negative and MARR is 15 percent. He doesn't have time to redo the analysis. Can you help him figure out the IRR?