Question: The time a construction crew takes to construct a building is normally distributed with mean 90 days and standard deviation 10 days. After construction, it
The time a construction crew takes to construct a building is normally distributed with mean 90 days and standard deviation 10 days. After construction, it takes additional time to install utilities and finish the interior. Assume the additional time is independent of the construction time, and is normally distributed with mean 30 days and standard deviation 5 days.
(a) Find the probability it takes at least 101 days for the construction of only a building.
(b) Find the probability it takes an average of 101 days for the construction of only four buildings.
(c) What is the probability that the total completion time for one building is at most 130 days?
(d) What is the probability that the average additional completion time for five buildings is at least 35 days?