A permanent flood-control dam is expected to have an initial cost of $2.8 million and an annual

Question:

A permanent flood-control dam is expected to have an initial cost of $2.8 million and an annual M&O cost of $20,000. In addition, minor reconstruction will be required every 5 years at a cost of $200,000. As a result of the dam, flood damage will be reduced by an average of $310,000 per year. Using an interest rate of 6% per year, the conventional B/C ratio will be closest to:

(a) 0.46

(b) 1.02

(c) 1.40

(d) 1.96

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Engineering Economy

ISBN: 978-0073523439

8th edition

Authors: Leland T. Blank, Anthony Tarquin

Question Posted: