In linear breakeven analysis, if process A has a variable cost of $45 per unit and process

Question:

In linear breakeven analysis, if process A has a variable cost of $45 per unit and process B has a variable cost of $31 per unit, which alternative would be preferred if the breakeven point is 7400 units and production is expected to be 6200 units?

(a) Process A

(b) Process B

(c) Process B if its fixed cost is lower than the fixed cost of Process A

(d) Cannot tell; need more information