Question: Two alternatives, identified as X and Y, are evaluated using the B/C method. Alternative Y has a higher total cost than X. If the B/C
Two alternatives, identified as X and Y, are evaluated using the B/C method. Alternative Y has a higher total cost than X. If the B/C ratios are 1.2 and 1.0 for alternatives X and Y, respectively, which alternative should be selected? Why?
Step by Step Solution
3.58 Rating (159 Votes )
There are 3 Steps involved in it
Alternative X should be sel... View full answer