Question: Two methods can be used for producing solar panels for electric power generation. Method 1 will have an initial cost of $550,000, an AOC of
Two methods can be used for producing solar panels for electric power generation. Method 1 will have an initial cost of $550,000, an AOC of $160,000 per year, and $125,000 salvage value after its 3-year life. Method 2 will cost $830,000 with an AOC of $120,000, and a $240,000 salvage value after its 5-year life. Assume your boss asked you to determine which method is better, but she wants the analysis done over a 3-year planning period. You estimate the salvage value of method 2 will be 35% higher after 3 years than it is after 5 years. If the MARR is 10% per year, which method should the company select?
Step by Step Solution
3.43 Rating (172 Votes )
There are 3 Steps involved in it
AW 1 550000AP103 160000 125000AF103 5500... View full answer