Question: Suppose you have a project whose discounted payback is equal to its termination date. What can you say for sure about its PI? (Hint: What
Suppose you have a project whose discounted payback is equal to its termination date.
What can you say for sure about its PI? (Hint: What will the project’s NPV be?)