Highrise Constructions Ltd had a large three-year project with total revenue of $5 000 000 and estimated

Question:

Highrise Constructions Ltd had a large three-year project with total revenue of $5 000 000 and estimated total costs of $4 200 000. The project was 25 percent complete at the end of the first year, 55 percent complete at the end of the second year, and 100 percent complete at the end of the third year. Revenues and costs were as estimated.

1. What profit was earned during the first year if the percentage of completion method was used?

2. What profit was earned during the second year if the percentage of completion method was used?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Financial Accounting An Integrated Approach

ISBN: 9780170349680

6th Edition

Authors: Ken Trotman, Michael Gibbins, Elizabeth Carson

Question Posted: