DC Watts, Inc., makes power cords for a variety of electronic products. Lately, it has been having
Question:
DC Watts, Inc., makes power cords for a variety of electronic products. Lately, it has been having significant problems with the quality of its output. It also appears that making a batch of power cords takes longer and longer. Donald Wright, the head of manufacturing, has just completed a study of one of the main power cord lines. The following is the list of activities, times, and costs estimates for the various activities.
It takes 0.5 minutes on the machine to make one power cord. The power cords normally sell for $8. After sorting out good from bad units, 80% were good units and 20% were bad.
REQUIRED:
a. Calculate the total elapsed time in this cycle.
b. Calculate the process time in this cycle. What percentage of time is used to complete process activities?
c. Determine how many power cords were successfully made during the morning shift.
d. Calculate the total cost of the operations.
e. Calculate the average cost of a good power cord.
f. Calculate the total process costs of operations. What percentage of cost is used for process activities?
g. Develop a rough profit analysis for the morning’s operations. Specifically, using the times and prices noted, determine how much revenue was generated by the morning’s production vs. how much cost was incurred. Set up your analysis as follows:
Revenue
Less: Process costs
Potential profit
Less: Non process costs
Profit (loss) for morning shift
h. What would you say to Donald about his operations? Why?
Step by Step Answer:
Managerial Accounting An Integrative Approach
ISBN: 9780999500491
2nd Edition
Authors: C J Mcnair Connoly, Kenneth Merchant