Question: During project execution, a third party, responsible for developing a web utility for a Government project, reports to the project manager. One of the technologies
During project execution, a third party, responsible for developing a web utility for a Government project, reports to the project manager. One of the technologies used in the development has become obsolete. The third party proposes an alternative. 1 action should the project manager take first? termine the impact on the overall project. gotiate the best price for the alternative. C. Assign extra resources to the project. D. Have the management sign-off on the new alternative.