Question: In a large, complex project, the authority to accept or reject a requested change should rest with the: A. Sponsor B. Client C. Project manager
In a large, complex project, the authority to accept or reject a requested change should rest with the:
A. Sponsor B. Client C. Project manager D. Change control board