Question: Resources leveling will generally: A. Increase total costs for the project. B. Push out the end date of the project. C. Require fewer resources. D.

Resources leveling will generally:

A. Increase total costs for the project.

B. Push out the end date of the project.

C. Require fewer resources.

D. Require more resources.