Question: A first-time project manager is trying to understand the difference between configuration control and change control. The difference is: Configuration control is focused on the
A first-time project manager is trying to understand the difference between configuration control and change control. The difference is:
Configuration control is focused on the specification of both the deliverables and the process, but change control is focused on identifying, documenting, and controlling changes to the project.
Configuration control is focused on ensuring that all changes are documented whereas change control is focused on the approval process.
Change control is focused on the specification of both the deliverables and the process whereas configuration control is focused on identifying, documenting and controlling changes to the project.
Change control is focused on ensuring that approved changes are documented and controlled whereas configuration control is focused on ensuring that changes are properly identified and approved by the change control board.