Question: A project charter that formally authorized a project was created. The project charter documented the initial requirements to satisfy stakeholders' needs and expectations. How often
A project charter that formally authorized a project was created. The project charter documented the initial requirements to satisfy stakeholders' needs and expectations. How often should the project charter be revised?
At the beginning, middle, and end of a project Once a month Project charter is usually not updated during the course of the project.
As required by the PMO
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts