Question: A project manager analyzed the projects communication requirements and decided that 10 out of the 30 stakeholders in the project would only need voicemail updates
A project manager analyzed the project’s communication requirements and decided that 10 out of the 30 stakeholders in the project would only need voicemail updates of certain information. This type of communication is:
Push communication Pull communication Interactive communication On-demand communication