Question: A project manager approaches you to understand the Work Breakdown Structure (WBS) in better detail. You tell her that: The WBS is a detailed project
A project manager approaches you to understand the Work Breakdown Structure (WBS) in better detail. You tell her that:
The WBS is a detailed project plan and includes the effort, resources, and dates on which the tasks for the project are complete.
The WBS is a task-oriented decomposition of work that identifies each task and the resource required to accomplish the task.
The WBS is a deliverable-oriented hierarchical decomposition of the work the project team must accomplish to meet project objectives.
The WBS is a Gantt chart that contains details about the project deliverables the project team must do.