Question: A project manager first creates an assumption log during the Develop Project Charter process and records all project assumptions and constraints. During which of the
A project manager first creates an assumption log during the Develop Project Charter process and records all project assumptions and constraints. During which of the following processes is the assumptions log updated and/or new assumptions and constraints added during the project execution?
Monitor and Control Project Work Close Project or Phase Direct and Manage Project Work Collect Requirements
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts