Question: A project manager has a problem with a team member's attendance, but every time the project manager schedules a meeting to discuss the problem, the
A project manager has a problem with a team member's attendance, but every time the project manager schedules a meeting to discuss the problem, the team member comes up with a reason they cannot attend at the last minute. Which conflict management technique is the team member exhibiting?
A. Passive-aggressive B. Covering up C. Diverting D. Withdrawing