Question: A project manager is estimating the project duration and finds that the only information available to him is a previous project that was quite different

A project manager is estimating the project duration and finds that the only information available to him is a previous project that was quite different from the current one. However, some portions of the previous project were similar to the current one. Which of the following tools is the project manager likely to use to compare current project's activity durations with the similar previous activities?

Analogous estimating Program Evaluation and Review Technique (PERT)

Three-point estimates Parametric estimating