Question: A senior project manager advises a first-time project manager that identifying risks is just one step. On a continuing basis, new risks need to be

A senior project manager advises a first-time project manager that identifying risks is just one step. On a continuing basis, new risks need to be identified, and existing risks need to be analyzed and tracked, and their status reported. All this is done as part of what process?

Direct and Manage Project Work Monitor and Control Project Work Perform Integrated Change Control Plan Risk Management