Question: . All EVT control account plans (CAPs) continuously measure project performance by relating which of the following 3 independent variables? a) Cost variance (CV), actual

. All EVT control account plans (CAPs) continuously measure project performance by relating which of the following 3 independent variables?

a) Cost variance (CV), actual costs (AC) and estimate at completion (EAC)

b) Planned value (PV), actual costs (AC) and cost performance index (CPI)

c) Planned value (PV), actual costs (AC) and earned value (EV)

d) Earned value (EV), cost performance index (CPI)

and schedule performance index (SPI)