Question: All requested changes to a contract go through Contract Change Control Systems of both parties. The Contract Change Control system documents all requested changes for

All requested changes to a contract go through Contract Change Control Systems of both parties. The Contract Change Control system documents all requested changes for future reference. However, requested but unresolved changes might not make it up to either party’s Change Control Systems. If you are contesting a dispute, where can you find a record of such requested changes?

Procurement management plan Project management plan Project correspondence Approved change requests log