Question: Anna has recently taken over a project as the project manager. The project is early in the executing phase. Although all the key stakeholders signed
Anna has recently taken over a project as the project manager. The project is early in the executing phase. Although all the key stakeholders signed off on the project scope statement, Anna learns that some of the key stakeholders do not fully understand the project scope.
The stakeholders’ constant support is crucial for the success of the project. What must Anna do?
Email the copy of the scope management plan to the key project stakeholders Don’t do anything since all the key project stakeholders signed the scope statement.
Email the copy of the scope statement to the key project stakeholders.
Conduct one-to-one meeting sessions with these key stakeholders to ensure they understand the project scope
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts