Question: As part of the procurement process, the procuring organization elected to have an estimate of costs prepared by an outside professional estimator. The estimator came

As part of the procurement process, the procuring organization elected to have an estimate of costs prepared by an outside professional estimator. The estimator came up with an estimate of $500,000.

However, the cost estimates prepared by prospective sellers were in the range of $200,000. How can this be best interpreted?

The procurement statement of work was deficient and ambiguous.

The professional estimator has inflated the estimate of costs.

The prospective sellers do not have the required skills to do the project.

Prospective sellers are trying to underbid and win the project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Fraud Examination Questions!