Question: . Based on the schedule and cost variance table above, what is the cost variance for Case 2? a) -1,000 b) 1,000 c) -2,000 d)
. Based on the schedule and cost variance table above, what is the cost variance for Case 2?
a) -1,000
b) 1,000
c) -2,000
d) 2,000