Question: Cost estimating should be performed: A. Before the work breakdown structure is created and before the budget is developed. B. Before the work breakdown structure
Cost estimating should be performed:
A. Before the work breakdown structure is created and before the budget is developed.
B. Before the work breakdown structure is created and after the budget is developed.
C. After the work breakdown structure is created and before the budget is developed.
D. After the work breakdown structure is created and after the budget is developed.