Question: During a work breakdown structure meeting, you have decomposed the deliverables into work packages and created your WBS dictionary. However, you now want to decompose

During a work breakdown structure meeting, you have decomposed the deliverables into work packages and created your WBS dictionary.

However, you now want to decompose the work packages to assist you in estimating, executing, and controlling the project. These decomposed work packages are:

Work packages can't be decomposed into smaller units Activities Milestones Control Accounts