Question: During the procurement process, a contractual relationship is established between a buyer and a seller. During the contract lifecycle, what is the correct sequence in
During the procurement process, a contractual relationship is established between a buyer and a seller. During the contract lifecycle, what is the correct sequence in which the following terminology is applied to a seller: Vendor, selected source, and bidder?
The seller is viewed first as a selected source, then as a bidder and then as a vendor.
The seller is viewed first as a vendor, then as a bidder and then as a selected source.
The seller is viewed first as a bidder, then as a selected source and then as a vendor.
The seller is viewed first as a bidder, then as a vendor, then as a selected source.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts