Question: If a project manager is recommending that immediate corrective action be taken, which process is he involved in? A. Qualitative Risk Analysis. B. Risk Management

If a project manager is recommending that immediate corrective action be taken, which process is he involved in?

A. Qualitative Risk Analysis.

B. Risk Management Planning.

C. Risk Identification.

D. Risk Monitoring and Control.