Question: If a task has been estimated at 0 = 4 days, P = 9 days, and M = 7, what is the standard deviation? A.
If a task has been estimated at 0 = 4 days, P = 9 days, and M = 7, what is the standard deviation?
A. 516 of a day.
B. 6.83 days.
C. 113 of a day.
D. 112 of a day.