Question: Julia is managing a complex industrial process reengineering project. She has identified all her key project stakeholders and has conducted individual interviews with them to
Julia is managing a complex industrial process reengineering project.
She has identified all her key project stakeholders and has conducted individual interviews with them to identify other project stakeholders, as well. However, Julia is still not satisfied with her project’s stakeholders list; she believes there may be more key external stakeholders missing from the list. What can help Julia in this situation?
Use stakeholder register templates from the organizational process assets Conduct more meetings with the key stakeholders Get over her fear and finalize the project stakeholder register Seek expert judgment from subject matter experts