Question: Lucy is managing a website development project in an agile environment. She wants to create a burndown chart to present the projects progress to the
Lucy is managing a website development project in an agile environment. She wants to create a burndown chart to present the project’s progress to the stakeholders. She adds a diagonal line representing the ideal burndown and a line for daily actual remaining work. She now needs to show the likely variance at the iteration completion. What should she do?
Add a forecast trend line to the ideal burndown line Add a correlation line between the daily actual remaining work and the ideal burndown Add a forecast trend line to the daily actual remaining work Add a median line between the daily actual remaining work and the ideal burndown