Question: Mary has recently finalized her project management plan and has gotten it approved. She is managing a complex manufacturing process improvement project. The project stakeholders'
Mary has recently finalized her project management plan and has gotten it approved. She is managing a complex manufacturing process improvement project. The project stakeholders' constant support and commitment are crucial for the success of the project. Which of the following are the most important stakeholder management processes at this stage?
Plan Stakeholder Engagement and Manage Stakeholder Engagement Identify Stakeholders and Plan Stakeholder Engagement Manage Stakeholder Engagement and Monitor Stakeholder Engagement Plan Stakeholder Engagement and Monitor Stakeholder Engagement