Question: Organizations develop change control procedures to ensure that: a) Changes are controlled by the Change Controller. b) All changes are requested, scheduled, and completed on
Organizations develop change control procedures to ensure that:
a) Changes are controlled by the Change Controller.
b) All changes are requested, scheduled, and completed on time.
c) All changes are authorized, tested, and recorded.
d) Management is advised of changes made to system.