Question: Project A would yield $100,000 in benefit. Project B would yield $250,000 in benefit. Because of limited resources, your company can perform only one of
Project A would yield $100,000 in benefit. Project B would yield
$250,000 in benefit. Because of limited resources, your company can perform only one of these. They elect to perform Project B because of the higher benefit. What is the opportunity cost of performing Project B ?
A. -$150,000. B. $150,000. C. -$100,000. D. $100,000.