Question: . The critical path in a schedule network is the path that: a) Takes the longest time to complete b) Must be done before any

. The critical path in a schedule network is the path that:

a) Takes the longest time to complete

b) Must be done before any other tasks

c) Allows some flexibility in scheduling a start time

d) Is not affected by schedule slippage