Question: 'The project has completed execution, and now it is time for the product of the project to be accepted. Who formally accepts the product? A.
'The project has completed execution, and now it is time for the product of the project to be accepted. Who formally accepts the product?
A. The project team and the customer.
B. The quality assurance team, senior management, and the project manager.
C. The sponsor, key stakeholders, and the customer.
D. The project manager, senior management, and the change control board.