Question: . The sequence of activities that cannot be delayed during the course of the project is referred to as the: a) Critical path b) Master
. The sequence of activities that cannot be delayed during the course of the project is referred to as the:
a) Critical path
b) Master schedule
c) Slack line
d) Action plan