Question: The technique most commonly used by project management software packages to construct a project schedule model is: Precedence diagramming method (PDM) Finish-to-Start (FS) Activity-In-Node (AIN)
The technique most commonly used by project management software packages to construct a project schedule model is:
Precedence diagramming method (PDM)
Finish-to-Start (FS)
Activity-In-Node (AIN)
Node-On-Activity (NOA)