Question: Which of the following process sequences is correct?: A. Create WBS, then Cost Budgeting, then Cost Estimating. B. Create WBS, then Cost Estimating, then Cost

Which of the following process sequences is correct?:

A. Create WBS, then Cost Budgeting, then Cost Estimating.

B. Create WBS, then Cost Estimating, then Cost Budgeting.

C. Cost Budgeting, then Cost Estimating, then Create WBS.

D. Cost Estimating, then Cost Budgeting, then Create WBS.