Question: Which of these is accurate regarding the Develop Schedule process? Schedules are optimized such that all noncritical activities have a zero total float. The critical

Which of these is accurate regarding the Develop Schedule process?

Schedules are optimized such that all noncritical activities have a zero total float.

The critical path method is a schedule network analysis technique that is performed using the schedule model.

Schedule compression shortens the project schedule while changing the project scope.
Schedule network analysis is a technique carried out once the schedule is approved.