Question: While executing the project plan, you discover that a component was missed during planning. The project schedule is not in danger, but the component is
While executing the project plan, you discover that a component was missed during planning. The project schedule is not in danger, but the component is not absolutely critical for go-live. What should you do?
A. Treat the component as a new project.
B. Reject the component as it would introduce unacceptable risk.
C. Appeal to the project sponsor for guidance.
D. Return to planning processes for the new component.