Question: While managing a large project, the project manager decided to include indirect costs as part of his cost estimate. If indirect costs are included in
While managing a large project, the project manager decided to include indirect costs as part of his cost estimate. If indirect costs are included in an estimate, which of the following is true?
Include indirect costs at the activity level or higher levels Include indirect costs at the activity level only Include indirect costs only in earned value measurements and not in cost estimates Exclude indirect costs in cost estimates