Question: While sequencing activities for a project, the project management team applied certain discretionary dependencies. This was based on their knowledge of best practices within the

While sequencing activities for a project, the project management team applied certain discretionary dependencies. This was based on their knowledge of best practices within the project application area. What is the potential risk involved in using such dependencies?

They can create fixed float values and create external dependencies.

They can create arbitrary float values and limit later scheduling options.

They can create arbitrary float values and create external dependencies.

They can create arbitrary float values and create mandatory dependencies.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Fraud Examination Questions!