Question: Why is the project change log a prime input to the Manage Stakeholder Engagement process? So that the changes and their impact can be communicated
Why is the project change log a prime input to the Manage Stakeholder Engagement process?
So that the changes and their impact can be communicated to the appropriate stakeholders So that the new identified changes can be appended to the log So that stakeholders can review the log and prioritize the issues So that the Integrated Change Control process is made redundant