Question: You have a schedule activity that can be delayed without delaying the early start date of any subsequent activities. This is an example of: Free
You have a schedule activity that can be delayed without delaying the early start date of any subsequent activities. This is an example of:
Free Float Lead Float Total Float Lag Float