Question: Your organization has a policy that any project changes that increase budget by more than 1.5% should be signed off by the project office. You
Your organization has a policy that any project changes that increase budget by more than 1.5% should be signed off by the project office.
You have a change that was requested by the customer that will increase the budget by 3%; however, the customer has offered to pay for all of this change and does not want to slow it down. Which option represents the BEST choice?
A. Approve the change yourself and take it to the project office after the work is complete.
B. Ask the customer to take the change to the project office and explain the situation.
C. Do not allow the change since it increases the budget by over 1.5%.
D. Take the change to the project office.