Question: Your team has encountered recent unanticipated problems. After extensive earned value analysis you determine that the project has a schedule performance index of .54 and
Your team has encountered recent unanticipated problems. After extensive earned value analysis you determine that the project has a schedule performance index of .54 and a cost performance index of 1.3. Additionally your customer has just requested a significant change.
What should you do?
A. Alert management about the schedule delays.
B. Alert management about the cost overruns.
C. Alert management about the scope change.
D. Reject the requested change.